Earthwork to be done on Bradley Waterpark Soon

By Callie Foster Oct 13, 2026 | 9:08 AM
At Monday Night’s Bradley Village Board meeting, trustees passed a resolution to accept a construction bid for the earthwork to be done on the indoor waterpark near exit 315 of I-57. Bradley Finance Director Rob Romo says Tenco Excavating was the only bidder.
The earthwork will cost over two million dollars for the indoor waterpark and is expected to take roughly four to six months to complete. Dirt should be moving on the site starting sometime this month with a groundbreaking ceremony to be announced soon.